Issue Date:
2/2/2009
Disassemble River Barge
Description:
The New York Power Authority the ("Authority"), Niagara Power Project, is seeking proposals from qualified contractors to remove from the Niagara River one (1) each Buckhorn Barge hereafter referred to as the ("Scrap Metal"). Removal includes the proper removal and disposal of stone ballast from the top of the barge. A fair-market credit to the Authority is expected from the steel recovered from the barge.
Bidders are hereby cautioned to make use of the New York Power Authority’s web site at www.nypa.gov in order to obtain current and complete bid documents, bid addenda, post-bid addenda and related notices. Bidders obtaining bid documents from sources other than www.nypa.gov web site do so at their own risk. Incomplete bid responses may be rejected by the Authority. To find the bid documents at the website Select Site: NIAGARA Category: MISCELLANEOUS SERVICES
Bidders must meet all Authority requirements including, but not limited to, Insurance, Safety & Security requirements, and Minority and Women Business Sub-Contracting Goals.
Proposal Due Date: 2/24/2009
Contract Term: As soon as possible after receipt of order
| Contact: |
Frank A. Giancola, Purchasing Manager
Niagara Power Project
Power Authority of New York
5777 Lewiston Road
Lewiston,NY 14092
(716) 286-6031
716-286-6054
frank.giancola@nypa.gov
|
| Submit To: |
Judith Fitzpatrick, Purchasing Clerk
Niagara Power Project
Power Authority of New York
5777 Lewiston Road
Lewiston,NY 14092
7162866037
7162866054
judy.fitzpatrick@nypa.gov
|
|